Poinciana Parkway Timeline

Poinciana Parkway discussions over the years

The following articles and dates describing the Poinciana Parkway history was put together based on internet search done under the term Poinciana Parkway. It is by no means complete but is an attempt to provide a brief history of the project.

Avatar’s Tony Iorio speaks about Poinciana Parkway plans at Poinciana Area Council (PAC) meeting. Iorio states that there were over 3,000 Poinciana homes constructed in 2005. Poinciana is among the top planned communities in the nation with this growth. Poinciana population identified at 57,000 people.
‘Anyone who navigates the roadways daily in Poinciana, a community nearing 60,000 residents, knows that morning and afternoon rush-hour traffic can make roads seem more like parking lots than highways.’ – Michael Freeman Feb 16,2006


‘$60M , 10-mile tool road to open in Poinciana next year’. Bill Orben Orlando Business Journal May 14,2007
Avatar – which needs the parkway in place to continue developing its Solivita active-adult community – is fronting the anticipated $60 million cost of the road, which has been in the planning stages since the early 1990’s.
‘Plans to build another road out of Poinciana through environmentally sensitive land face continued delays following requests for more information from state agencies.’ Steve Magruder – Osceola News Gazette July 13,2007



Avatar and Osceola County lose out after applying for Federal TIGER grant to help fund Poinciana Parkway. ‘Avatar is building the road, and we hope to partner with Avatar on this’ – Osceola County Manager Don Fisher – June 2010


‘Transportation Meeting Takes Wrong Turn’ – Haines City Reporter – Mike Grogan
‘Residents wanted to hear gridlock solutions, not long range plans’

Feb 2006
Dec 2006
July 2007
June 2010


Polk and Osceola County Commissions approve agreements with Avatar allowing the developer to use condemnation powers to acquire rights of way for the project. The agreements call for Avatar to open the road by Oct 31,2008.

Oct 2011
Please click here to read article?
Please click here to read article?
Please click here to read article?
Please click here to read article?
Please click here to read article?

This page last modified on Monday, November 28, 2011

Avatar and Osceola county apply for federal funding to build road
Please click here to read article?
2012
Jan 2012
National Publication 'Business Journals' Jan 6,2012 Ranks Poinciana Last in America for Commuters
Please click for more information